Its cost

Construction costs

The plant’s actual construction costs (excluding conveyance to La Coujoune) amounted to 1 634 000 € or 411 €/PE including general infrastructure, pipe connections between filters and ponds, over-dimensioning for future extension. The project was financed in partnership with:
Adour-Garonne CCTVA - Union Européenne - CG82

 

 

 

Allocation of funds

Organisms Works-water conveyance Works-plant Works-total Studies and others General total %
European union 0 € 181 000 € 181 000 € 19 000 € 200 000 € 9 %
Water agency 171 350 € 708 940 € 880 290 € 91 900 € 972 190 € 45 %
Department council 0 € 122 094 € 122 094 € 13 566 € 135 660 € 8 %
CCTVA 145 650 € 621 966 € 767 616 € 79 534 € 847 150 € 37 %
Total 317 000 € 1 634 000 € 1 951 000 € 204 000 € 2 155 000 € 100 %

Studies: project manager, advices, topography, geotechnical, technique control, security control… - Others: plot purchase, electricity connection…

Operating costs

Based on the figures of 2010, the first year of normal operation for approx. 2900 PE:

  2010
Total % €/Eh
Charge moyenne 2900 EH    
Entretien courant 400 h x 20€/h = 8 000 € 22 2
Entretien des filtres 620 h x 20€/h = 12 400 € 34 3
Entretien espaces verts 500 h x 20€/h = 10 000 € 28 2.5
       
Hydrocureur 7 U x 172 = 1 205 € 3 0.3
Electricité 48 366 kWh x 0.08 = 3 942 € 11 1
Eau potable 652 m³ x 1.2 = 782 € 2 0.2
       
Total 39 329 € 100 9

Filter maintenance = weeding + reed cutting + disposal of stubbles…. % = = percentage of total annual costs…. €/PE = cost per nominal PE, i.e. for 4000 PE. Not included: sludge scrubbing from the primary filters (every 10 to 15 years) and replacement of equipment.